Performance objective | Screening criteria | Alternative options | |
---|---|---|---|
1 |
Minimise the potential for instability, waste breakout or leachate breakout due to inundation by floodwaters or scouring from floodwaters |
Siting - landfill not sited in 1 in 100-year or less floodplain |
Design - landfill designed to remove the risks of waste breakout, leachate breakout or instability associated with flooding or inundation |
2 |
Minimise the potential for failure of basal liner and leachate collection system |
Siting - landfill not sited in an inter-tidal zone |
None |
3 |
Minimise the potential for failure of basal liner and leachate collection system |
Siting - over 1 m separation between underside of landfill basal liner and maximum expected groundwater level |
Design - landfill designed to remove the risk of failure of the basal liner or leachate collection system from groundwater pressure under the liner system |
4 |
Minimise the potential for failure of basal liner and leachate collection system |
Siting - landfill not within a geothermally active area |
Design - landfill designed to remove the risk of failure of the basal liner or leachate collection system from geothermal activity |
5 |
Minimise risks to landfill stability (including effects on liner integrity and leachate collection system) |
Siting - landfill not sited over compressible or unstable foundation materials |
Design - landfill designed to remove risks from compressible or unstable foundation materials to liner integrity, landfill stability and leachate system operation |
6 |
Avoid contamination of adjacent surface water bodies with leachate or contaminated stormwater |
Siting - no direct pathway from landfill to a significant surface water body |
Design - stormwater, groundwater and leachate management systems designed to mitigate risks to surface water bodies |
7 |
To protect the coastal marine area from adverse environmental impacts associated with the landfill |
Siting - landfill not sited in coastal marine area |
None |
8 |
Avoid contamination of a viable groundwater supply |
Siting - landfill not sited over permeable material |
Only site over highly permeable in-situ materials such as sands or gravels (perm > 1x10-5 m/s) if the landfill does not overlie a viable groundwater supply Siting - landfill not sited over viable groundwater supply Design - higher standard of engineered containment that accounts for the minimal natural containment available and includes a base and side composite liner 1.5 mm HDPE overlying 600 mm clay (10-9 m/s) (or the equivalent) |
9 |
Avoid contamination of a viable groundwater supply |
Siting - landfill not sited over a viable groundwater supply |
Siting/design - only site over viable groundwater supply if the combination of engineered and natural containment results in negligible risk of contamination of the groundwater supply Siting - Aquitard between base of landfill and viable groundwater supply Design - high standard of engineered containment including a base and side composite liner 1.5 mm HDPE overlying 600 mm clay (10-9 m/s) |
10 |
Remove the risks from active faults on the containment system |
Siting - landfill not sited in an area subject to seismic instability |
Design - designed to remove risks from seismic activity to liner integrity, landfill stability and leachate system operation |
11 |
Effective containment of waste, leachate and landfill gas |
Design - landfill has a base and side composite liner 1.5 mm HDPE overlying 600 mm clay (max permeability 10-9 m/s) |
Design - alternative landfill liner design that provides equivalent level of risk mitigation, considered with reference to resistance to chemical degradation, hydraulic containment, physical strength and deformation characteristics, general installation procedures and expected service life (see Appendix E) |
12 |
Effective containment of waste, leachate and landfill gas |
Design - leachate collection system designed to ensure the maximum leachate head over liner is < 300 mm |
None |
13 |
Effective containment of waste, leachate and landfill gas |
Design/operation - for sites with a total design capacity over 1,000,000 m3, a landfill gas flaring system |
Design/operation - alternative landfill gas treatment system or use that provides equivalent level of risk mitigation |
14 |
Effective containment of waste, leachate and landfill gas, and control of water infiltration into landfill |
Operation - effective use of daily and intermediate cover |
None |
15 |
Prevention of landfill fires |
Operations - management plan includes measures to prevent landfill fires |
None |
16 |
Minimise the risks associated with inappropriate waste disposal |
Operations - management plan requires documentation and record keeping of waste volumes, types and source |
None |
17 |
Minimise the risks associated with inappropriate waste disposal |
Operations - management plan requires a licensing system for all non-municipal waste generators. The licensing system shall require adequate information to ensure that the landfill operator is satisfied that the waste meets the Landfill Waste Acceptance Criteria |
None |
18 |
Minimise the risks associated with inappropriate waste disposal |
Operations - management plan defines waste acceptance criteria monitoring procedures - a minimum of 1 in 50 commercial/industrial loads inspected |
None |
19 |
Minimise the potential for instability, waste breakout or leachate breakout due to inundation by floodwaters or scouring from floodwaters |
Operations - management plan ensures adequate maintenance of surface water control system |
None |
20 |
Avoid contamination of adjacent surface water bodies with leachate or contaminated stormwater |
Operation - landfill management plan ensures adequate control of surface water |
None |
See more on...
Appendix D: Landfill classification - Class A requirements
May 2004