Go back to "7. Appendix"

Table 4: Summary of decisions sought

Submission no.

Submitter

Position

Approve application

Compensation for loss of property value

Decline application

Specific issues to be mitigated

Other

Comments

24

Birdsall, Mr Anthony and Koster, Mrs Linda

Not stated

     

Yes

 

Monitoring of groundwater and Contact to provide water if contaminated. Locate station on Eastern boundary. Structures screened.

9

Department of Conservation

Neutral

       

Yes

Supports efforts to decrease discharge to the Waikato River. No relief sought.

8

Dutton Price, Miss Lynley; Dutton Price, Miss Alison

Oppose

 

Yes

       

13

Ellery, Mr Grant and Mrs Francis

Oppose

 

Yes

     

Shelter belt to screen plant and noise. Provision of alternative water supply if contaminated.

12

Energy Efficiency and Conservation Authority

Support

Yes

         

4

Environment Waikato

Neutral

     

Yes

 

Consents should be consistent with Council geothermal policy and existing consents.

7

Fish & Game NZ, Eastern Region

Support

Yes (implied)

         

19

Geotherm Group Ltd

Mixed

     

Yes

 

Inclusion of conditions to ensure adverse impacts on the Geotherm Project are avoided, remedied or mitigated. Issues include reinjection sites, combined H2S and noise emissions, geothermal features and export to national grid.

5

Hansen, Mr Graham and Mrs Isobel

Oppose

 

Yes

     

Alternatively if granted applicant should be required to mitigate the traffic effects at the intersection. Change to intersection layout is required.

18

Houghton, Mr Ray

Oppose

   

Yes

     

1

Macphal, Ms Sarah; Campbell, Mr Ian

Oppose

       

Yes

None stated.

21

Major Electricity Users’ Group

Neutral

       

Yes

Request Board give little weight to reasons for Minister calling in the proposal.

10

McGrath, JJ and JM and Family

Mixed

     

Yes

 

Reinjection into same geothermal system. Confine operations to area stated.

15

McLachlan, Mr Alistair; McLachlan, Ms Ava Marie; MacPower Ltd

Mixed

     

Yes

 

Inclusion of conditions to ensure no impact on the Geotherm project. Issues include cumulative air and noise emissions, reinjection of geothermal fluids, transmission capacity, impacts on existing consent holders, extension of land area and recent drilling of a new well.

6

Ministry of Economic Development

Support

Yes

       

Approve application for land-use consent.

22

Tauhara North 3B Trust

Mixed

     

Yes

 

Consultation, communication and regular updates on reinjection plans and monitoring adjacent to interests of the Trust.

17

Taupo District Council

Neutral

     

Yes

 

Conditions on traffic, earthworks, visual, noise, hazardous substances, natural hazards, cultural and cumulative effects. The 6,500 tpd cooling water blowdown and condensate onto land should be reinjected.

14

Te Kapa o Te Rangiita ki Oruanui

Neutral

     

Yes

 

Clarify issues not resolved in pre-consultation process. Issues include staged reinjection impacts on taonga, groundwater integrity, impacts on sites of significance in the cultural impact assessment and ability to exercise their relationship with their taonga. Pre-hearing meeting requested and decision on hold.

23

Toyota, Anna and Karz

Mixed

       

Yes

None stated.

11

Transit New Zealand, Hamilton Regional Office

Oppose

   

Yes

   

Alternatively upgrade road or divert construction traffic.

16

Tuwharetoa Maori Trust Board

Neutral

     

Yes

 

Clarify issues not resolved in pre-consultation process. Issues include staged reinjection impacts on taonga, groundwater integrity, impacts on sites of significance in the cultural impact assessment and ability to exercise their relationship with their taonga. Pre-hearing meeting requested and decision on hold.

2

Vanner, Mr Brett and Mrs Heather

Neutral

     

Yes

 

Give careful consideration to construction of visible structures and consider burying pipes.

20

Waikato Raupatu Trustee Company Ltd (Tainui)

Not stated

     

Yes

 

Include a condition to ensure that within 12 months of the Crown settling any claim made under the provisions of the Treaty of Waitangi Act (1975) the consent holder will review conditions of the consent to ensure consent is in alignment with the provisions of any such settled claim.

3

Wind Farm Developments (Australia) Ltd

Neutral

     

Yes

 

Require condition ensuring project shall not result in the loss of generation from any existing or approved renewable generation projects as at the 7/03/08.

 

Total

 

3

3

2

12

4

 
 

Percentage

 

12.5%

12.5%

8.3%

50.0%

16.7%

 

 

See more on...