When processing applications, councils must comply with the timeframes in the RMA.
Table 3: Total working days for processing non-notified consents and notified consents
Type of application | Total working days |
---|---|
Non-notified consent (no hearing) | 20 |
Non-notified consent (with hearing) | 50 |
Non-notified fast track consent (District land-use consent with controlled activity status) |
10 |
Limited notified consent (with hearing) | 100 |
Limited notified consent (no hearing) | 60 |
Publicly notified consent (with hearing) | 130 |
Publicly notified consent (no hearing) | 60 |
Note these are indicative, and will vary if councils need to request further information or approvals.