Applying for requiring authority status

This guidance outlines the application process network utility operators must follow when applying for requiring authority status. It also outlines their role and lists current and revoked requiring authorities.

Changes resulting from the Planning Act 2026

The Planning Act 2026 received Royal assent on 30 September 2026 and will be commenced in stages as it operates alongside the RMA during a transition period. The Planning Act 2026 provides for a new designating authority regime which will ultimately replace the requiring authority regime under the RMA. Designating authorities are entities who may hold or propose a designation under the Planning Act 2026, although aspects of the new designation regime will not come into effect until the end of the transition period.  

During the transition period entities may still apply to be approved as a requiring authority under the RMA. Under the Planning Act 2026, all requiring authorities under the RMA, whether approved before 30 September 2026 or subsequently, must be treated as an equivalent designating authority under the new legislation. No new or additional application is necessary for approval as a designating authority where an entity is already a requiring authority. 

Alternatively, entities may choose to apply for approval as a designating authority under the Planning Act 2026, for example where they meet a designating authority definition which has no equivalent under the requiring authority regime. Entities approved as designating authorities can have designations included in district plans under certain circumstances and, if so, will meet the definition of a requiring authority in the RMA in relation to that designation.

Guidance on the new planning system can be found at planning.govt.nz.

Who can be a requiring authority

Requiring authorities can be:

  • a Minister of the Crown
  • a local authority
  • a network utility operator approved as a requiring authority under the RMA.

Network utility operators can apply to the Minister for the Environment for approval to become a requiring authority for the purposes of a particular work, project or a particular network utility operation.

Network utility operators are defined in section 166 of the RMA and include entities that distribute gas, petroleum, geothermal energy, telecommunications, electricity, water and wastewater, or construct or operate roads, railway lines and airports.

What requiring authorities can do

Requiring authorities have significant powers.

They can:

  • apply to the local authority to designate land. (A designation is a provision in a district plan that gives notice to the community that a requiring authority intends to use land in the future for a particular work or project)
  • undertake works in an emergency and get resource consents after the work has been done
  • apply to the Minister of Land Information to use the compulsory acquisition powers in the Public Works Act 1981
  • go on to private land (after giving notice) to undertake investigations under the Public Works Act 1981.

Revocation of requiring authority status

Under the RMA, the Minister for the Environment may revoke requiring authority status under section 167(5) of the RMA if satisfied that a requiring authority is either:

  • no longer likely to undertake or complete a project, work or network utility operation
  • unlikely to satisfactorily carry out any of its responsibilities as requiring authority
  • no longer a network utility operator.