National Environmental Standards for Electricity Network Activities

In force

The National Environmental Standards for Electricity Network Activities (NES-ENA) provide nationally consistent planning rules for electricity transmission, electricity distribution and electric vehicle charging infrastructure. They enable network operation, maintenance, upgrading and development while managing environmental, amenity and safety effects

Official title

Resource Management (National Environmental Standards for Electricity Network Activities) Regulations 2026

Lead agency

Ministry for Cities, Environment, Regions and Transport and Ministry of Business, Innovation and Employment

In force from

14 January 2010

Amended regulations in force from 8 October 2026

Recent amendments

Electricity network amendments - September 2026

Following public consultation in 2025, the regulations have been amended and renamed the National Environmental Standards for Electricity Network Activities (NES-ENA). 

The amendments expand the standards beyond existing transmission activities to cover electricity distribution networks and incorporate the electric vehicle charging infrastructure provisions introduced in 2026. They also introduce new rules to protect electricity networks from incompatible development and update standards for routine network work. 

See the Gazette Notice for the NES-ENA.

View the NES-ENA amendments (New Zealand Legislation website)

Electric Vehicle Charging Infrastructure amendments – April 2026 

Changes to the NES-ETA for Electric Vehicle Charging Infrastructure were gazetted on 9 April 2026 and come into force on 7 May 2026. Further amendments to the NES-ETA are also expected in 2026.

See the NZ Gazette notice for the NES-ETA 

View the Recommendations and Decisions report for the NES-ETA amendments.

See the NES-ETA regulatory impact statement

Why they are needed

The NES-ENA is intended to: 

  • provide a nationally consistent planning framework for electricity transmission, electricity distribution and EV charging infrastructure 
  • enable more routine operation, maintenance, upgrading, replacement and development work where environmental effects can be appropriately managed 
  • reduce unnecessary consenting costs and delays, support electrification and network resilience, and protect electricity infrastructure from incompatible nearby activities. 

What they do

The NES-ENA set out national activity rules and consent requirements for electricity transmission, electricity distribution and EV charging infrastructure. They also manage some third-party activities near electricity lines. 

The regulations specify: 

  • which activities are permitted when specified conditions are met 
  • the consent pathways and matters councils may consider when permitted activity standards are not met 
  • national standards for existing and new electricity distribution assets, including lines, support structures and cabinets 
  • rules for EV charging infrastructure and for subdivision, buildings, structures and earthworks near electricity networks. 

The transmission provisions continue to apply principally to transmission lines that were operational, or able to be operated, on 14 January 2010. The NES-ENA also apply to electricity distribution assets and EV charging infrastructure as specified in the regulations. Electricity substations are not regulated by the NES-ENA. 

The NES-ENA now include nationally consistent rules for electricity distribution lines, support structures, cabinets and associated network activities. 

The NES-ENA does not provide for the construction of new transmission lines. 

Permitted activities

Permitted activities now include:

  • operating and maintaining existing transmission and distribution lines

  • installing, replacing or maintaining conductors, wires and network telecommunications equipment where the relevant standards are met

  • safety and operational signs associated with electricity networks 
  • altering, relocating or replacing support structures, distribution lines and cabinets within specified limits
  • the construction, maintenance, operation, upgrade, replacement and removal of electricity vehicle charging infrastructure
  • carrying out earthworks, vegetation clearance, blasting and protective-coating work.

the objectives and policies of the relevant plan or proposed plan. 

Controlled activities 

The council may impose conditions on specified matters but cannot decline consent unless insufficient information is provided. Some activities that fail permitted activity conditions will be controlled. Examples include undergrounding overhead transmission lines, moving poles and towers more than a specified distance from their existing location, and discharges to water that are more than minor. 

Restricted discretionary activities 

The council may decline consent or grant it subject to conditions on specified matters. Some activities that fail permitted activity terms and conditions will be restricted discretionary. Examples include earthworks on potentially contaminated land and constructing new distribution lines or cabinets in natural areas or historic heritage place or area. 

Discretionary activities 

The council may decline consent or grant it with or without conditions. Any transmission activities not listed elsewhere in the NES would be discretionary. Councils also have discretion under several rules designed to protect the electricity network. 

Non-complying activities 

The council may decline consent or grant it with or without conditions. It may grant consent only if satisfied that adverse environmental effects will be no more than minor, or the activity will not be contrary to the objectives and policies of the relevant plan or proposed plan. Non-complying status has been reserved for non-compliance with electric and magnetic field, radiofrequency field and national grid rules where the permitted activity standards are not met, posing potential risks to human health and safety. 

It is the council’s decision whether to publicly notify a resource consent application or not. If the council does decide to publicly notify a resource consent application, then it will consider submissions in deciding whether to grant consent or not.

Further information on notification decision-making is available on the Quality Planning website.

Rights of access to private land

The RMA cannot confer any rights of access to private land. Existing access provisions (under the Electricity Act or through existing easement agreements) will not be affected in any way by the NES.

About current plan rules

From commencement, the NES-ENA apply directly without reliance on district plan rules for most electricity network activities. Equivalent plan rules are displaced unless the regulations expressly allow a district or combined plan rule to be more lenient. 

The NES-ENA contains leniency provisions for specified electricity distribution and EV charging rules. Where those provisions apply, a more lenient plan rule may continue to operate. The exceptions to leniency are in relation to electric and magnetic fields, radiofrequency fields and national grid rules, to ensure these rules provide standard levels of protection. 

Plan rules addressing effects that are outside the scope of the NES-ENA may still apply. Councils should review and update provisions that duplicate or conflict with the NES-ENA. 

Guidance

Changes to National Environmental Standards for Electricity Network Activities 

Factsheet summarising amendments made to the NES-ENA in September 2026, including change in name and scope to the National Environmental Standards for Electricity Network Activities 

See Updating National Direction: Changes to National Environmental Standards for Electricity Network Activities

Additional technical guidance on these amendments will be made available soon. 

Changes to National Environmental Standards for Electricity Transmission Activities – Electric Vehicle charging 

Factsheet summarising amendments made to the NES-ETA in April 2026 for electric vehicle charging infrastructure

Updating National Direction: Changes to National Environmental Standards for Electricity Transmission Activities – Electric Vehicle charging

Changes to National Environmental Standards for Electricity Transmission Activities: Introduction

  • For local authorities, Transpower and lines operators – to assess the resource consent requirements for the maintenance and upgrade of existing transmission lines and determine which activities are permitted.
  • For local authorities – to understand how the NES implements the National Policy Statement on Electricity Transmission (the NPS).
  • For members of the public – to understand the broad direction of the NES and how it relates to the NPS.

National Environmental Standards for Electricity Transmission Activities: Introduction 

What you need to refer to

The NES-ENA incorporate the following material by reference: 

  • New Zealand Standard NZS 6803:1999 Acoustics – Construction noise 
  • German Standard DIN 4150-3:1999 Structural Vibration – Effects of Vibration on Structures. 
  • NZS 2772.1:1999 — Radiofrequency fields – Maximum exposure levels – 3 kHz to 300 GHz. 
  • AS/NZS 2772.2:2016 — Radiofrequency fields – Part 2: Principles and methods of measurement and computation – 3 kHz to 300 GHz 
  • NZS 6801:2008 — Acoustics – Measurement of environmental sound 
  • NZS 6802:2008 — Acoustics – Environmental noise  

This incorporated material can be inspected by appointment, free of charge, at the Ministry for Cities, Environment, Regions and Transport’s head office.  

To arrange an appointment, contact enquiries@mcert.govt.nz.  

Photocopying of incorporated material will not be permitted.

Alternatively the incorporated material above may be purchased from:

Standards New Zealand Limited
Radio New Zealand House
Level 10, 155 The Terrace
Wellington 6011
Freephone 0800 782 632
Email: enquiries@standards.co.nz
Website: http://www.standards.co.nz/